Radiography Project Cuts Down Costs and Labor

Service Line

Conventional NDT

Situation

An engineer we had worked with prior had reached out to us on behalf of the Oil and Gas company he was working with.  They had a large project with 12 X-Ray trucks from 6 different NDT companies.

They were not getting the efficiency or quality they needed, so they asked if we could start with one truck to catch the project up. Within 6 months, we had 4 X-Ray rigs covering what the 8 trucks had been doing previously. They were able to narrow their project down to only 2 companies instead of 12. PROtect was the last company to leave that project when it was finished.

The Result

The client saved a significant amount of money because of our efficiency and ability to better manage their needs and risk.

How Can We Help?

Safety, reliability, and compliance obligations can be the difference between a sustainable and profitable business and one that is not.

Contact Us